Metal Industries
What we are offering:
a. Electrical & automation for EAF & LF
b. Electrical & automation for Ladle turret
Mobarakeh Steel Complex is one of our clients that use our products in its steel making plant since 1981.
References:
- Study, Design, Manufacture, Erection & Commissioning for revamping of Ladle Turret Control System in MOBARAKEH STEEL COMPANY (MSC).- Design, Manufacture, Erection & Commissioning of MOBARAKEH STEEL COMPANY (MSC) Ladle Transfer Car control system.
a. Mould oscillator ,casting segments
b. Roller tables electrical and control
c. Cutting machine control system
a. Electrical & drives from Preheating furnace to coilers
b. Roughing mill drive
c. Rolling tables
d. side Guides and screw down drives lopper
e. Cascade Finishing stands drives
f. Coiler, pinch rolls wrapper roll drives and automation
g. cooling bed and rolling bed drives and automation
h. Roll change mechanism control
Our successful experience in SABA steel Complex covers from initial stages of design activities till commissioning and performance guarantee tests in electrical and automation systems.
References:
- Participation in design and commissioning of Electrical & automation systems of ESCO Expansion Project (SABA) Hot Strip Mill with Ansaldo Sistemi Industriali.
- Hot commissioning of 3rd coiler in MOBARAKEH STEEL COMPANY (MSC) Hot Strip Mill with Procurement of missing parts (mechanical and electrical and electronic parts.
- Commissioning and Final Tuning of Hot Strip mill 7th Stand Power drives and control system in MOBARAKEH STEEL COMPANY.
- Design, Construction, Erection and Commissioning of main stands DC drive panels using high power 16000 Amp drives in Esfahan Steel Company.
- Design, Construction, Erection and Commissioning of roller ways AC drives using redundant AC drives in Esfahan Steel Company.
- Design, Construction, Erection and Commissioning of level 0, level 1 and level2 automation system in Esfahan steel company heavy section mill 650. Minimum stoppage time
and using last technologies such as redundant PLC, Industrial networks and fully digital huge drives are most indicated features of this project.
- Design & software development of Billet Temperature Monitoring system in Esfahan Steel Company
a. Electrical & drives & automation from Preheating furnace to cooling bed, cutting machine
a. Electrical& automation for Pickling lines
b. Electrical& automation for Tandem mill
c. Material tacking
Tow Stands tandem cold mill and five stands tandem cold mill in Mobarakeh Steel Complex are our recent activities in this field.
Development and putting in services the technological process control tasks such as: Hydraulic Gap Control, Work Roll Bending, Automatic Gauge Control, Automatic Tension Control, Automatic Flatness Control with using Real Time Controllers are just some part of our activities in these two plants
References:
- Participation in design and Commissioning of automation systems (level0, level 1, level2) of Two Stand Tandem Reversing Mill With Ansaldo sistemi industriali in
MOBARAKEH STEEL COMPANY .
- Basic study and Survey for revamping of Temper Mill in Mobarakeh Steel Complex
- Participation in design and Commissioning of automation systems of double stand cold reduction mill (Temper Mill) in Mobarakeh Steel Complex.
- Participation in design and Commissioning of automation systems of Five Stands Tandem Mill in Mobarakeh Steel Complex.
- Complete Revamping with S7 PLC's of control system for old Hydraulic Systems for Temper Mill in Mobarakeh Steel Company.
a. Electrical& automation of Inspection lines
b. Electrical& automation of Corrective lines
c. Electrical& automation of Galvanizing lines
d. Electrical& automation of Skin pass
e. Electrical& automation of Temper mill
f. Electrical& automation of light &heavy gauge
New Continues pickling line and new corrective line in Mobarakeh Steel Complex are last experiences in this field.
Using special and high technology field instruments and sophisticated Human Machine Interface (HMI) are the main features for this plants that our specialists could arrive in maximum satisfaction and performance in short time.
Reference:
- Study ,Design ,Construction and performing revamping of electrical and control system over head traveling Cranes in order to Prevent Rails& Wheels grinding as EPC using PLC
and AC Drives for various plants system in Mobarakeh Steel Company.
1) Design and Commissioning of ESCO Expansion Project (SABA) Hot Strip Mill With PLC & AMS & Drive.
2) Design Erection and Commissioning of MSC Two Stand Reversing Mill With PLC & AMS & Drive.
3) Design and Commissioning of MSC Corrective Line with PLC & AMS & Drive.
4) Design and Commissioning of MSC Process Line with PLC & AMS & Drive.
5) Design and Commissioning of MSC Temper Mill with PLC & AMS & Drive.
6) Design and Commissioning of MSC Hot Strip mill 3rd Coiler with Drive & Electronic cards.
7) MSC Temper Mill Revamping.
8) Design and Erection and Commissioning of MSC Cranes with PLC & Drive to Prevent Rail & Wheel Grinding.
9) Commissioning and Final Tuning of MSC Hot Strip mill 7th Stand.
10) Commissioning and tuning up of Harir Khuzestan Tissue Plant.
11) Commissioning, modification and Training of GE Static Var Control System (30,5 KV 2x100 MVA).for MSC
12) Electrical Revamping of Deir ez Zor paper mill in Syria.
13) Design, Manufacture, Erection & Commissioning of MSC Ladle Turret Control System.
14) Design and manufacturing of high precise measuring displacement sensor with Accuracy 0.5 Micron for tandem mill of MSC.
15) Design construction, Erection & Commissioning of chain Conveyor in MSC Old Pickling Line.
16) Design construction, Erection & Commissioning of Compressor control System in Hamedan power Plant.
17) Design construction, Erection & Commissioning of MSC Ladle Transfer Car.
18) Design and perform Billet Temperature Monitoring of ESCO for Greco
19) Revamping of ESCO 650 Heavy Section Mill by S7-PLC & 16000A Drives
20(Design and Commissioning of automation system for New Pickling line of MSC
21(Design and Commissioning of automation system for New Corrective Line of MSC
22(Design and Commissioning of automation system for New Inspection Line of MSC
23(Supervision of Electrical and automation in revamping of five stands tandem mill of MSC
24(Revamping in control & automation of hydraulic system of temper mill QLR in MSC